Search

Athletic Facilities LED Lighting Conversion

  1. Capital Improvement Projects
Parks and Recreation

Harris Center

425 Perry St

MARK STEVEN KRANZ

MARK STEVEN KRANZ

budget strategic planning mgr

Project Overview

This project will replace all existing Metal Halide lighting at athletic fields with LED lighting. Metal Halide lights will no longer be produced after being phased out by the Department of Energy. The facilities include the Auburn Softball Complex, Margie Piper Bailey Field, the Samford Avenue Tennis Center, the Auburn Wire Road Soccer Complex, the Shug Jordan Soccer fields, Duck Samford baseball fields, the Yarbrough Clay Tennis Courts, and Felton Little Park.

The project was completed on Oct 9, 2024 with a total capital budget of $3,799,434.11.

Duck Samford baseball fields, playground to reopen Oct. 10

LED light installation at Samford Avenue Pickleball and Tennis Center now complete

Photos